Loading Flipbook...
contents
CREDITS
Project Director
Page
Mr Lim Kian Peng
Project Director’s Note
Deputy Directors
Mr. Lim Kian Peng
Mr Sihan Sadikin
Ms Juila Lim
Contributors
LTA Project Teams for
Keppel Station and Tunnels
(C882)
Cantonment Station
(C883)
Prince Edward Road Station and
Tunnels (C885)
Cut-and-Cover Tunnels at Marina
Bay Area (C886)
Kim Chuan Depot Extension
(C821A)
LTA Community Partnership Managers
Ms Hema
Mr Eric Soh
3
Did you know?
Constructing underground linkway connecting
CC31 Cantonment Station and its Entrances
(C883) using trenchless construction method
4
Did you know?
Challenges faced by C886 in removing the buried
obstructions left by reclamation and development
of Marina Bay
5
Ms Nurly Sudin
Mr Md Ridwan
Main Contractors
China State Construction
Engineering Corporation
Limited (Singapore Branch) and
Nishimatsu Construction Co. Ltd
Joint Venture
China State Construction
Engineering Corporation Limited
(Singapore Branch)
China Railway Tunnel Group Co.,
Ltd (Singapore Branch)
Koh Brothers Building and Civil
Engineering Contractor (Pte) Ltd
Woh Hup (Private) Limited
Graphical illustration of Circle Line 6
Keeping Track
Keeping Track and In Touch
6
7
8
Project Director’s Note
Dear Residents and Stakeholders
Welcome to the 3rd issue of the Circle Line 6 (CCL6)
Project Newsletter!
Year 2020 marks a challenging year for the world amidst
the COVID-19 pandemic. I hope that all of you have been
staying well and safe during this Post COVID-19 Circuit
Breaker.
The construction for the five CCL6 civil contracts, namely
Keppel Station, Cantonment Station, Prince Edward Road
Station, Cut and Cover Tunnels at Marina Bay Area and
Kim Chuan Depot Extension has resumed after fulfilling
the requirements of the COVID-Safe Restart criteria for the
construction sector. It is especially crucial to work closely
with the authorities and the contractors in achieving
a COVID-Safe Workforce, COVID-Safe Worksite and
COVID-Safe Accommodation and Transportation while
proceeding with the construction works cautiously and
to mitigate the risks of any potential COVID-19 spread
as we resume our works on site.
With the COVID-Safe control measures in place amidst
abiding with the advisories from Ministry of Health (MOH),
Ministry of Manpower (MOM) and Building Construction
Authority (BCA), I would like to assure you that my team
is making the best effort in minimising any inconvenience
to the stakeholders while ensuring a safe and healthy
environment for the stakeholders and our workforce. I seek your understanding and support as we strive to complete
this 4km long project during this unprecedented period. When completed, it will close the loop for the Circle Line
MRT network.
Once again, I am extremely grateful for the support given by you over the past years. Let’s continue to stay strong and
connected as we get through this pandemic. Thank you and take care of yourself, and each other.
LIM KIAN PENG
Director (Rail Expansion)
Civil Team 1
3
Did you know?
CONSTRUCTING ENTRANCES USING PIPE JACKING METHOD
(CC31 CANTONMENT STATION)
Constructing Underground Linkway Connecting CC31
Cantonment Station and its Entrances Using Trenchless
Construction Method
The proposed Cantonment Station has four entrances
sited at strategic locations to serve the stakeholders in
the vicinity of Keppel Road, Spottiswoode Park Road
and Everton Road. Three of the entrances are connected
to the station by underground linkway from the
concourse level of the entrances. These underground
linkway will be constructed using trenchless construction
method.
A series of steel pipes will be
first installed horizontally by
Pipe Jacking Method with MicroTunnelling Boring Machine
(MTBM) to form a safe temporary
underground support between
the
station
and
entrance.
Once completed, mining will
be carried out to remove the
earth within the temporary
underground support and brace
with temporary steel framing. The
underground linkway will then be
built progressively. Throughout
the entire construction process,
the surrounding and adjacent
structures will be instrumented
and closely monitored.
The key advantage of adopting this construction
methodology is to minimise disruptions and inconvenience to the public and stakeholders, as well
as to avoid the need to divert the affected utilities and
roads. Notwithstanding that the construction works
could be carried out safely, it also reduces the impact to
the surrounding environment during construction, such
as minimizing the construction noise, as compared to
the traditional cut and cover method.
Currently the installation of the steel pipes for the
temporary underground support works at various
underground linkway is progressing well.
Underground Linkway
Layout of CC31 Cantonment Station
Top
member
Diagonal
member
Vertical
member
1.2m Dia. Steel pipes
Bottom
member
Micro-tunnelling Boring Machine: Illustration of water nozzles while pipe jacking
to reduce soil cohesiveness
4
Illustration of steel pipes installed horizontally to form a safe temporary
underground support
Did you know?
CHALLENGES FACED BY C886 IN REMOVING THE BURIED OBSTRUCTIONS
LEFT BY RECLAMATION AND DEVELOPMENT OF MARINA BAY
Most sections of the cut-and-cover tunnels connecting
Prince Edward Road station to Marina Bay station
constructed under Contract 886 (C886) are built in
reclaimed land.
The area next to Shenton Way has gone through
several reclamation phases since the founding of
modern Singapore. Many foundations and underground
structures were left behind during the reclamation
and development of the Marina Bay area. Some of the
obstructions include structures of PSA Marina Wharf and
container storage areas, Finger Pier, Telok Ayer Basin and
South Pier, Telok Telok Ayer Basin underpass, AYE/South
Quay viaduct have to be removed for C886 to construct
the cut-and-cover tunnels. Smaller items such as big
steel chains, rubber tires and broken ship parts were also
removed during diaphragm wall construction.
Broken ship parts found during Diaphragm wall construction
In purple: Obstructions to be removed to construct the cut-and-cover tunnels
5